Example: Phase - Revit Element Result with Ideate XRay

Here’s an example of the type of content embedded in Ideate XRay. There are more than 50 unique Revit invisibility results possible within the product itself.

 

When a “Phase — Created” or “Phase — Demolished” result is returned by Ideate XRay, the Phase Filter of the view is set to not display the element's phase status.


To fix this issue, consult your BIM manager and then complete one of the following changes. We recommend that you address the problem in this order:


1. Is the Element on the Incorrect Phase?

If the hidden element is not on the correct phase, use the Properties palette to adjust the Phase Create or Phase Demolished setting.


The text displayed in the Ideate XRay — Show Results dialog provides important information about the phase state of the selected element, as shown in yellow below. The element selected while using Ideate XRay will be selected upon exiting the program to support making a change with the Properties palette if the phase is incorrect. If the element's phase is correct, check the phase of the Target View. See below. 

Why is this invisible - Ideate XRay

2. Is the Target View the Correct Phase?

If the Target View is not on the correct phase, you can edit the phase settings by selecting once within the view and then using the Properties palette to adjust the view. If the Phase setting is not editable, then the View Template is controlling this setting - contact your BIM Manager to adjust the View Template assignment or the View Template properties. If both the element and the phase are correct, then the last culprit will be the Phase Filter settings.


3. Change the Phase Filter

The view may have a Phase Filter setting that impacts the selected elements’ visibility. In Revit, the Phase settings are accessed from the Manage tab on the Phasing panel as shown below. 

Change the Phase Filter

Explore recent posts

15@15: Mastering Revit Key Schedules with Ideate BIMLink
By Kim DeLashmit June 9, 2025
TRAINING - VIDEO | Master Key Schedules in Revit with Ideate BIMLink. Learn how to create, manage, and optimize them for better data control and project efficiency. Take your Revit data management to the next level with Ideate BIMLink.
The Wait Is Almost Over: Upcoming Release of Ideate Software for Revit 2023–2026!
By Kim DeLashmit June 9, 2025
NEWS - ARTICLE | We know many of you have been eagerly awaiting the next release of Ideate Software—and we’re just as excited to share it with you! In late June, we’ll be launching updated versions of the Ideate Software bundle for Autodesk Revit 2023 through 2026. Whether you’re working in the latest version or supporting projects in previous releases, this update is for you.
15@15: Picture Integration: Embedding Excel Images in Revit
By Kim DeLashmit May 20, 2025
TRAINING - VIDEO | Import and scale embedded Excel images in Revit with Ideate Sticky. Enhance project communication by seamlessly integrating visuals into your Revit files.
15@15: Excel-lent Start-Up Views in Revit
By Kim DeLashmit May 5, 2025
TRAINING - VIDEO | Integrate Excel data seamlessly into Revit with Ideate Sticky. Create and publish information sheets as startup views for instant access to key project details. Enhance communication and efficiency with Ideate Sticky.
Show More